Huntsville Christian Church

171 Indian Creek Road

Huntsville, Alabama 35806

(256) 864-2220

Home

Location

Calendar

Youth

Ministries

Policies

Links

Contact

 

OPERATIONS MINISTRY TEAM PAGE

 


      This year has been very busy for Operations. We moved forward on many fronts to ensure the Huntsville Christian Church building and properties were useable and pleasing to the eye. As in the past, the Team faced many challenges and with God’s grace we were able to complete several projects and start the process to complete more. Below is a break down of the projects and their status. These are just the major projects that took more time and effort. Several smaller projects did occur which were completed by one or more Team member.

Roof – We continued to have leaks in the roof. Leaks started at the corners of the dormers shortly after the building was built and continued over the years. We have made many attempts to fix these leaks by hiring contractors and by getting on the roof ourselves. Alan Anderson headed up a day long effort to take apart a lot of the metal on the dormers, re-sealed many areas, and then reinstalled the metal. This had very little effect on the leaks. Other attempts included resealing some joints and screwheads. Finally Mark Wheat had enough and took this on as his personal project. He hired roofing contractor he was pleased with from work completed on his house. They surveyed the roof and looked long and hard at the leaks from inside the building. After all these years they discovered the issue. The roof changes pitch about midway down and at this pitch change the metal is to overlap several inches so water does not back up under the joint and leak inside the building. The joint only had about a one inch overlap. During hard rains water does indeed back up and leak inside. Mark did reseal this area and we will buy a better sealing compound and seal the joint. This is a short term fix that will last about a year. A long term fix is to add more metal and build the joint properly. This is at a higher expense and is included in next year’s capital expenditures.

Lights – New, very much needed lights have been installed on the new parking lot to the west and a larger four fixture unit replaced the existing two fixture unit on the old, main parking lot. These lights greatly helped visibility at night and security. Two fixture units have recently been installed at the end of the main parking lot. As time and money become available, we will install more lighting along the secondary drove (to the new parking lot) and the back side of the church.

Clearing – We continue to clear more of our land to the east of the building. It is hoped the low area between the building and Dry Creek can be used for a soccer field. The local soccer administration will be contacted to see if they will put in a field under a lease agreement. We will clear the tree line between the church property and the cotton field to the south so the church is more visible from Old Monrovia. We would also like to clear more brush and small trees next to Dry Creek so we can have a more “park” like setting in this area. We need to give many thanks to Eric Stogner for supplying all kinds of equipment to make this all possible. He has really stepped up – thanks Eric!!

Land – As we grow we will need to look at additional land for expansion. Kenny Watts has been actively researching the possible procurement of the cotton field to our south – about 5 acres now with the expansion of Old Monrovia taking a couple of acres. In the past the owner of this property has verbally given us the first right of refusal. Kenny is putting a plan together to present to the owner. This plan includes coordinating with the city of Huntsville to accelerate the timeline to put in a green-way on the sewer easement. If we can obtain the land we would donate a small section that could be used as the southern entrance and parking. A pavilion would be installed and dedicated to the Blakes (current owners). The green-way would be called the Cemetery Trail as there are three old slave cemeteries along this easement. Frank Fiala has joined Kenny in this hunt which continues.

Carpet – The carpet in the office area need to be replaced. We have ordered the carpet and have it scheduled to install. By the time this report is out it should be complete. This has been a longer project than planned due to the time it took to order the carpet and schedules to remove/replace the furniture.

Rewire the Stage – Benny Sharp put together a team to rewire the stage. This helped remove the unsightly cords that crossed the stage to the speakers and microphones. Many thanks Benny!

Scout Projects – Many scout projects have been completed this year. They include: Clearing a trail to the amphitheater on the northeast corner of our property. Build seating for the amphitheater to seat about 100 people. Build a temporary /removable bridge over Dry Creek for access to the amphitheater. Apply mulch to the amphitheater seating area to control mud issues the give it a finished look. Build a fence on the west side of the building to hide the HVAC units. Future projects include helping with Ms Bobbie’s bridge and cleaning out and removing the old shed and surrounding brush on the north side of the building. Many thanks to the Scouts for their efforts, to Kenny Watts to his guidance, and the Operations Team for their help.

Future Projects

Baptistery: During a work day Greg Perkins and crew refinished the lid of the baptistery. We will continue to work on the baptistery to make it more presentable. One thing we did include in the next year’s budget is a heater and filter/chemical system. This will help with the mold issue by the introduction of chemicals in the water and it will save embarrassing moments by keeping the water temperature consistent.

Walk to New Parking Lot: A walk has been planned to connect the new parking lot to the church at the back double doors. We have received low bids but they could not get us in their schedule and the high bids were, well, too high. We plan to complete this project ourselves if we can not find a good concrete contractor to give us a good price.

Bridge: This is known as “Ms Bobbie’s Bridge.”  Mark Wheat is planning on building this bridge in the near future. He has a plan together and a scout to help in the building process to earn his Eagle Scout. It will connect the south front lawn to the picnic area.

Parking Lots: A capital expenditure line item has been put in next years budget to reseal and re-stripe both parking lots. This will help the longevity of the lots to protect our investment.

Reorganizing Operations – We have taken the task to reorganize Operations. The goal is to get more people involved, but more importantly to bring up people to make for disciplines in Christ’s name. The Team will have Sub teams to include: Outsourcing, Grounds, Building, Finance, and Publicity. Phil Hall and Frank Fiala are meeting with Bob Csikos once a week to get this effort underway. Bob will help us understand the area of discipleship and to assist in bringing our vision to the church body. We have made good progress and have named Frank as the Lead for Grounds and Leonard Dollarhide as the Lead, with Lewis Smith as his alt Lead, for Outsourcing. Naming the Lead for Building is underway, and Finance is running smoothly so it will remain as-is for now. We have added internal publicity to the Publicity Team so this Team will be reevaluated.

In conclusion, many thanks need to go out to a lot of people that have stepped up to help out Operations during work days and to fill in as needed. We have a lot of responsibility to ensure this church facility functions well. It is very important that new visitors see us as a body that cares about keeping God’s house well kept and appreciated. Thanks everyone!!



..Back to Ministries Page

Last Updated on 5/22/2007